Using PIPS to Minimize Causes of Delay in Saudi Arabian Construction Projects

University Case Study

Majed Alzara, Jacob Kashiwagi, Dean Kashiwagi, Abdulrahman Al-Tassan

    Research output: Contribution to journalArticle

    5 Citations (Scopus)

    Abstract

    Saudi Arabia has been facing issues with completing construction projects on time and on budget. It has been documented that 70% of public construction projects are delayed. A case study was performed at a University campus in northern Saudi Arabia, identifying the major causes of project delays. The University was experiencing delays from 50% to 150%. The delay factors were gathered from the University Projects Director. The University's delay factors were then compared to delay factors experienced on Saudi construction projects, identified by performing a literature research. The comparison identified nine causes of delays that both studies documented. The study also proposes a solution to minimize the nine major delay factors. A literature research identified one construction management method, the Performance Information Procurement System (PIPS), has documented multiple times its ability to improve project performance and minimize delays.

    Original languageEnglish (US)
    Pages (from-to)932-939
    Number of pages8
    JournalProcedia Engineering
    Volume145
    DOIs
    StatePublished - 2016

    Fingerprint

    Information systems

    Keywords

    • best value
    • delay project causes and factors
    • performance information procurement system (PIPS)
    • public construction
    • Saudi Arabia

    ASJC Scopus subject areas

    • Engineering(all)

    Cite this

    Using PIPS to Minimize Causes of Delay in Saudi Arabian Construction Projects : University Case Study. / Alzara, Majed; Kashiwagi, Jacob; Kashiwagi, Dean; Al-Tassan, Abdulrahman.

    In: Procedia Engineering, Vol. 145, 2016, p. 932-939.

    Research output: Contribution to journalArticle

    Alzara, Majed ; Kashiwagi, Jacob ; Kashiwagi, Dean ; Al-Tassan, Abdulrahman. / Using PIPS to Minimize Causes of Delay in Saudi Arabian Construction Projects : University Case Study. In: Procedia Engineering. 2016 ; Vol. 145. pp. 932-939.
    @article{37359b44e53e40fdae89a861abadaafd,
    title = "Using PIPS to Minimize Causes of Delay in Saudi Arabian Construction Projects: University Case Study",
    abstract = "Saudi Arabia has been facing issues with completing construction projects on time and on budget. It has been documented that 70{\%} of public construction projects are delayed. A case study was performed at a University campus in northern Saudi Arabia, identifying the major causes of project delays. The University was experiencing delays from 50{\%} to 150{\%}. The delay factors were gathered from the University Projects Director. The University's delay factors were then compared to delay factors experienced on Saudi construction projects, identified by performing a literature research. The comparison identified nine causes of delays that both studies documented. The study also proposes a solution to minimize the nine major delay factors. A literature research identified one construction management method, the Performance Information Procurement System (PIPS), has documented multiple times its ability to improve project performance and minimize delays.",
    keywords = "best value, delay project causes and factors, performance information procurement system (PIPS), public construction, Saudi Arabia",
    author = "Majed Alzara and Jacob Kashiwagi and Dean Kashiwagi and Abdulrahman Al-Tassan",
    year = "2016",
    doi = "10.1016/j.proeng.2016.04.121",
    language = "English (US)",
    volume = "145",
    pages = "932--939",
    journal = "Procedia Engineering",
    issn = "1877-7058",
    publisher = "Elsevier BV",

    }

    TY - JOUR

    T1 - Using PIPS to Minimize Causes of Delay in Saudi Arabian Construction Projects

    T2 - University Case Study

    AU - Alzara, Majed

    AU - Kashiwagi, Jacob

    AU - Kashiwagi, Dean

    AU - Al-Tassan, Abdulrahman

    PY - 2016

    Y1 - 2016

    N2 - Saudi Arabia has been facing issues with completing construction projects on time and on budget. It has been documented that 70% of public construction projects are delayed. A case study was performed at a University campus in northern Saudi Arabia, identifying the major causes of project delays. The University was experiencing delays from 50% to 150%. The delay factors were gathered from the University Projects Director. The University's delay factors were then compared to delay factors experienced on Saudi construction projects, identified by performing a literature research. The comparison identified nine causes of delays that both studies documented. The study also proposes a solution to minimize the nine major delay factors. A literature research identified one construction management method, the Performance Information Procurement System (PIPS), has documented multiple times its ability to improve project performance and minimize delays.

    AB - Saudi Arabia has been facing issues with completing construction projects on time and on budget. It has been documented that 70% of public construction projects are delayed. A case study was performed at a University campus in northern Saudi Arabia, identifying the major causes of project delays. The University was experiencing delays from 50% to 150%. The delay factors were gathered from the University Projects Director. The University's delay factors were then compared to delay factors experienced on Saudi construction projects, identified by performing a literature research. The comparison identified nine causes of delays that both studies documented. The study also proposes a solution to minimize the nine major delay factors. A literature research identified one construction management method, the Performance Information Procurement System (PIPS), has documented multiple times its ability to improve project performance and minimize delays.

    KW - best value

    KW - delay project causes and factors

    KW - performance information procurement system (PIPS)

    KW - public construction

    KW - Saudi Arabia

    UR - http://www.scopus.com/inward/record.url?scp=84999791298&partnerID=8YFLogxK

    UR - http://www.scopus.com/inward/citedby.url?scp=84999791298&partnerID=8YFLogxK

    U2 - 10.1016/j.proeng.2016.04.121

    DO - 10.1016/j.proeng.2016.04.121

    M3 - Article

    VL - 145

    SP - 932

    EP - 939

    JO - Procedia Engineering

    JF - Procedia Engineering

    SN - 1877-7058

    ER -