The importance of proper scheduling of energy equipment in combined heat and power plants for buildings

A case study

T Agami Reddy, Itzhak Maor

Research output: Chapter in Book/Report/Conference proceedingConference contribution

Abstract

There is increasing interest in using Combined Heat and Power (CHP) systems to supply the energy needs in commercial/institutional buildings. However, due to the large diurnal and seasonal variability in building thermal and electric loads, such systems in buildings (BCHP) require more careful and sophisticated operation as compared to those in industrial CHP. Operating such systems consists of two separate issues: (i) equipment scheduling which involves determining which of the numerous equipment combinations to operate, i.e., is concerned with starting or stopping prime movers, boilers and chillers; and (ii) the second and lower level type of control, called supervisory control, which involves determining the optimal values of the control parameters (such as loading of primemovers, boilers and chillers) under a specific combination of equipment schedule. This paper is concerned with both these aspects, and presents case study results of a school under real-time electrical pricing (RTP) located in New York City, NY. A school has been selected for study because of its high diurnal and seasonal load variability. The approach first involved simulating the buildings using a detailed building energy simulation program to obtain hourly electrical and thermal loads which were then used to size the BCHP system components. Subsequently, a certain number of days in the year were identified, and simulation runs were performed for optimal scheduling control as well as for all the feasible (but non-optimal) equipment combinations. The energy and cost implications of operating the BCHP system in a non-optimal manner under various scheduling combinations are presented and discussed.

Original languageEnglish (US)
Title of host publicationProceedings of the ASME 3rd International Conference on Energy Sustainability 2009, ES2009
Pages1-13
Number of pages13
Volume2
DOIs
StatePublished - 2009
EventASME 3rd International Conference on Energy Sustainability, ES2009 - San Francisco, CA, United States
Duration: Jul 19 2009Jul 23 2009

Other

OtherASME 3rd International Conference on Energy Sustainability, ES2009
CountryUnited States
CitySan Francisco, CA
Period7/19/097/23/09

Fingerprint

Cogeneration plants
Scheduling
Thermal load
Boilers
Electric loads
Costs
Loads (forces)
Hot Temperature

Keywords

  • CHP for schools
  • Combined heat and power
  • Cost optimization
  • Cost penalties of non-optimal control
  • Optimal scheduling control

ASJC Scopus subject areas

  • Energy Engineering and Power Technology
  • Renewable Energy, Sustainability and the Environment

Cite this

Reddy, T. A., & Maor, I. (2009). The importance of proper scheduling of energy equipment in combined heat and power plants for buildings: A case study. In Proceedings of the ASME 3rd International Conference on Energy Sustainability 2009, ES2009 (Vol. 2, pp. 1-13) https://doi.org/10.1115/ES2009-90004

The importance of proper scheduling of energy equipment in combined heat and power plants for buildings : A case study. / Reddy, T Agami; Maor, Itzhak.

Proceedings of the ASME 3rd International Conference on Energy Sustainability 2009, ES2009. Vol. 2 2009. p. 1-13.

Research output: Chapter in Book/Report/Conference proceedingConference contribution

Reddy, TA & Maor, I 2009, The importance of proper scheduling of energy equipment in combined heat and power plants for buildings: A case study. in Proceedings of the ASME 3rd International Conference on Energy Sustainability 2009, ES2009. vol. 2, pp. 1-13, ASME 3rd International Conference on Energy Sustainability, ES2009, San Francisco, CA, United States, 7/19/09. https://doi.org/10.1115/ES2009-90004
Reddy TA, Maor I. The importance of proper scheduling of energy equipment in combined heat and power plants for buildings: A case study. In Proceedings of the ASME 3rd International Conference on Energy Sustainability 2009, ES2009. Vol. 2. 2009. p. 1-13 https://doi.org/10.1115/ES2009-90004
Reddy, T Agami ; Maor, Itzhak. / The importance of proper scheduling of energy equipment in combined heat and power plants for buildings : A case study. Proceedings of the ASME 3rd International Conference on Energy Sustainability 2009, ES2009. Vol. 2 2009. pp. 1-13
@inproceedings{e3280680117246c6bebc6b204cc980b7,
title = "The importance of proper scheduling of energy equipment in combined heat and power plants for buildings: A case study",
abstract = "There is increasing interest in using Combined Heat and Power (CHP) systems to supply the energy needs in commercial/institutional buildings. However, due to the large diurnal and seasonal variability in building thermal and electric loads, such systems in buildings (BCHP) require more careful and sophisticated operation as compared to those in industrial CHP. Operating such systems consists of two separate issues: (i) equipment scheduling which involves determining which of the numerous equipment combinations to operate, i.e., is concerned with starting or stopping prime movers, boilers and chillers; and (ii) the second and lower level type of control, called supervisory control, which involves determining the optimal values of the control parameters (such as loading of primemovers, boilers and chillers) under a specific combination of equipment schedule. This paper is concerned with both these aspects, and presents case study results of a school under real-time electrical pricing (RTP) located in New York City, NY. A school has been selected for study because of its high diurnal and seasonal load variability. The approach first involved simulating the buildings using a detailed building energy simulation program to obtain hourly electrical and thermal loads which were then used to size the BCHP system components. Subsequently, a certain number of days in the year were identified, and simulation runs were performed for optimal scheduling control as well as for all the feasible (but non-optimal) equipment combinations. The energy and cost implications of operating the BCHP system in a non-optimal manner under various scheduling combinations are presented and discussed.",
keywords = "CHP for schools, Combined heat and power, Cost optimization, Cost penalties of non-optimal control, Optimal scheduling control",
author = "Reddy, {T Agami} and Itzhak Maor",
year = "2009",
doi = "10.1115/ES2009-90004",
language = "English (US)",
isbn = "9780791848906",
volume = "2",
pages = "1--13",
booktitle = "Proceedings of the ASME 3rd International Conference on Energy Sustainability 2009, ES2009",

}

TY - GEN

T1 - The importance of proper scheduling of energy equipment in combined heat and power plants for buildings

T2 - A case study

AU - Reddy, T Agami

AU - Maor, Itzhak

PY - 2009

Y1 - 2009

N2 - There is increasing interest in using Combined Heat and Power (CHP) systems to supply the energy needs in commercial/institutional buildings. However, due to the large diurnal and seasonal variability in building thermal and electric loads, such systems in buildings (BCHP) require more careful and sophisticated operation as compared to those in industrial CHP. Operating such systems consists of two separate issues: (i) equipment scheduling which involves determining which of the numerous equipment combinations to operate, i.e., is concerned with starting or stopping prime movers, boilers and chillers; and (ii) the second and lower level type of control, called supervisory control, which involves determining the optimal values of the control parameters (such as loading of primemovers, boilers and chillers) under a specific combination of equipment schedule. This paper is concerned with both these aspects, and presents case study results of a school under real-time electrical pricing (RTP) located in New York City, NY. A school has been selected for study because of its high diurnal and seasonal load variability. The approach first involved simulating the buildings using a detailed building energy simulation program to obtain hourly electrical and thermal loads which were then used to size the BCHP system components. Subsequently, a certain number of days in the year were identified, and simulation runs were performed for optimal scheduling control as well as for all the feasible (but non-optimal) equipment combinations. The energy and cost implications of operating the BCHP system in a non-optimal manner under various scheduling combinations are presented and discussed.

AB - There is increasing interest in using Combined Heat and Power (CHP) systems to supply the energy needs in commercial/institutional buildings. However, due to the large diurnal and seasonal variability in building thermal and electric loads, such systems in buildings (BCHP) require more careful and sophisticated operation as compared to those in industrial CHP. Operating such systems consists of two separate issues: (i) equipment scheduling which involves determining which of the numerous equipment combinations to operate, i.e., is concerned with starting or stopping prime movers, boilers and chillers; and (ii) the second and lower level type of control, called supervisory control, which involves determining the optimal values of the control parameters (such as loading of primemovers, boilers and chillers) under a specific combination of equipment schedule. This paper is concerned with both these aspects, and presents case study results of a school under real-time electrical pricing (RTP) located in New York City, NY. A school has been selected for study because of its high diurnal and seasonal load variability. The approach first involved simulating the buildings using a detailed building energy simulation program to obtain hourly electrical and thermal loads which were then used to size the BCHP system components. Subsequently, a certain number of days in the year were identified, and simulation runs were performed for optimal scheduling control as well as for all the feasible (but non-optimal) equipment combinations. The energy and cost implications of operating the BCHP system in a non-optimal manner under various scheduling combinations are presented and discussed.

KW - CHP for schools

KW - Combined heat and power

KW - Cost optimization

KW - Cost penalties of non-optimal control

KW - Optimal scheduling control

UR - http://www.scopus.com/inward/record.url?scp=77953753839&partnerID=8YFLogxK

UR - http://www.scopus.com/inward/citedby.url?scp=77953753839&partnerID=8YFLogxK

U2 - 10.1115/ES2009-90004

DO - 10.1115/ES2009-90004

M3 - Conference contribution

SN - 9780791848906

VL - 2

SP - 1

EP - 13

BT - Proceedings of the ASME 3rd International Conference on Energy Sustainability 2009, ES2009

ER -