Resource Modeling for Advanced Technology Facilities

Digdarshan Karki, Allan D. Chasey

Research output: Chapter in Book/Report/Conference proceedingConference contribution

Abstract

To meet the technology requirements outlined in the International Technology Roadmap for Semiconductors (ITRS), semiconductor-manufacturing facilities must be built quickly, more cost effectively, and with high quality standards. The construction industry has traditionally experienced difficulties in maintaining a balance between supply and demand of labor for these high tech facilities due to the cyclical swings and localized nature of the semiconductor industry. When construction is in high demand, skilled labor generally is in short supply. This is particularly true for a semiconductor manufacturing facility where unique skill sets are pivotal for successful completion of a fast-paced, capital-intensive project requiring high caliber skilled labor. How can the design/construction industry deal with this issue of unavailability of skilled labor? One approach could be to better utilize existing training resources. Alternately, improved resource forecasting could result in plans that would better match the number of new employees with projected industry needs. To address these issues, a research project was undertaken by CREATE, an advanced technology research consortium at Arizona State University, to identify the resource requirements for the design and construction of a semiconductor manufacturing facility. The research study outlines the skills and labor requirements from programming (initial design) to the completion of a model base-build facility. The results from this research indicate a high demand for a skilled labor force, especially for the mechanical and electrical trades, during the construction phase. Data collected from additional fabrication facilities will help create a resource model, which will assist in forecasting the demand of skilled labor for a proposed project.

Original languageEnglish (US)
Title of host publicationContruction Research Congress, Winds of Change: Integration and Innovation in Construction, Proceedings of the Congress
EditorsK.R. Molenaar, P.S. Chinowsky
Pages121-129
Number of pages9
StatePublished - 2003
EventConstruction Research Congress, Winds of Change: Integration and Innovation in Construction, Proceedings of the Congress - Honolulu, HI., United States
Duration: Mar 19 2003Mar 21 2003

Other

OtherConstruction Research Congress, Winds of Change: Integration and Innovation in Construction, Proceedings of the Congress
CountryUnited States
CityHonolulu, HI.
Period3/19/033/21/03

Fingerprint

Personnel
Semiconductor materials
Construction industry
Industry
Fabrication
Costs

ASJC Scopus subject areas

  • Engineering(all)

Cite this

Karki, D., & Chasey, A. D. (2003). Resource Modeling for Advanced Technology Facilities. In K. R. Molenaar, & P. S. Chinowsky (Eds.), Contruction Research Congress, Winds of Change: Integration and Innovation in Construction, Proceedings of the Congress (pp. 121-129)

Resource Modeling for Advanced Technology Facilities. / Karki, Digdarshan; Chasey, Allan D.

Contruction Research Congress, Winds of Change: Integration and Innovation in Construction, Proceedings of the Congress. ed. / K.R. Molenaar; P.S. Chinowsky. 2003. p. 121-129.

Research output: Chapter in Book/Report/Conference proceedingConference contribution

Karki, D & Chasey, AD 2003, Resource Modeling for Advanced Technology Facilities. in KR Molenaar & PS Chinowsky (eds), Contruction Research Congress, Winds of Change: Integration and Innovation in Construction, Proceedings of the Congress. pp. 121-129, Construction Research Congress, Winds of Change: Integration and Innovation in Construction, Proceedings of the Congress, Honolulu, HI., United States, 3/19/03.
Karki D, Chasey AD. Resource Modeling for Advanced Technology Facilities. In Molenaar KR, Chinowsky PS, editors, Contruction Research Congress, Winds of Change: Integration and Innovation in Construction, Proceedings of the Congress. 2003. p. 121-129
Karki, Digdarshan ; Chasey, Allan D. / Resource Modeling for Advanced Technology Facilities. Contruction Research Congress, Winds of Change: Integration and Innovation in Construction, Proceedings of the Congress. editor / K.R. Molenaar ; P.S. Chinowsky. 2003. pp. 121-129
@inproceedings{0b809933080f4e27ba60a6c50d0e1ec2,
title = "Resource Modeling for Advanced Technology Facilities",
abstract = "To meet the technology requirements outlined in the International Technology Roadmap for Semiconductors (ITRS), semiconductor-manufacturing facilities must be built quickly, more cost effectively, and with high quality standards. The construction industry has traditionally experienced difficulties in maintaining a balance between supply and demand of labor for these high tech facilities due to the cyclical swings and localized nature of the semiconductor industry. When construction is in high demand, skilled labor generally is in short supply. This is particularly true for a semiconductor manufacturing facility where unique skill sets are pivotal for successful completion of a fast-paced, capital-intensive project requiring high caliber skilled labor. How can the design/construction industry deal with this issue of unavailability of skilled labor? One approach could be to better utilize existing training resources. Alternately, improved resource forecasting could result in plans that would better match the number of new employees with projected industry needs. To address these issues, a research project was undertaken by CREATE, an advanced technology research consortium at Arizona State University, to identify the resource requirements for the design and construction of a semiconductor manufacturing facility. The research study outlines the skills and labor requirements from programming (initial design) to the completion of a model base-build facility. The results from this research indicate a high demand for a skilled labor force, especially for the mechanical and electrical trades, during the construction phase. Data collected from additional fabrication facilities will help create a resource model, which will assist in forecasting the demand of skilled labor for a proposed project.",
author = "Digdarshan Karki and Chasey, {Allan D.}",
year = "2003",
language = "English (US)",
isbn = "0784406715",
pages = "121--129",
editor = "K.R. Molenaar and P.S. Chinowsky",
booktitle = "Contruction Research Congress, Winds of Change: Integration and Innovation in Construction, Proceedings of the Congress",

}

TY - GEN

T1 - Resource Modeling for Advanced Technology Facilities

AU - Karki, Digdarshan

AU - Chasey, Allan D.

PY - 2003

Y1 - 2003

N2 - To meet the technology requirements outlined in the International Technology Roadmap for Semiconductors (ITRS), semiconductor-manufacturing facilities must be built quickly, more cost effectively, and with high quality standards. The construction industry has traditionally experienced difficulties in maintaining a balance between supply and demand of labor for these high tech facilities due to the cyclical swings and localized nature of the semiconductor industry. When construction is in high demand, skilled labor generally is in short supply. This is particularly true for a semiconductor manufacturing facility where unique skill sets are pivotal for successful completion of a fast-paced, capital-intensive project requiring high caliber skilled labor. How can the design/construction industry deal with this issue of unavailability of skilled labor? One approach could be to better utilize existing training resources. Alternately, improved resource forecasting could result in plans that would better match the number of new employees with projected industry needs. To address these issues, a research project was undertaken by CREATE, an advanced technology research consortium at Arizona State University, to identify the resource requirements for the design and construction of a semiconductor manufacturing facility. The research study outlines the skills and labor requirements from programming (initial design) to the completion of a model base-build facility. The results from this research indicate a high demand for a skilled labor force, especially for the mechanical and electrical trades, during the construction phase. Data collected from additional fabrication facilities will help create a resource model, which will assist in forecasting the demand of skilled labor for a proposed project.

AB - To meet the technology requirements outlined in the International Technology Roadmap for Semiconductors (ITRS), semiconductor-manufacturing facilities must be built quickly, more cost effectively, and with high quality standards. The construction industry has traditionally experienced difficulties in maintaining a balance between supply and demand of labor for these high tech facilities due to the cyclical swings and localized nature of the semiconductor industry. When construction is in high demand, skilled labor generally is in short supply. This is particularly true for a semiconductor manufacturing facility where unique skill sets are pivotal for successful completion of a fast-paced, capital-intensive project requiring high caliber skilled labor. How can the design/construction industry deal with this issue of unavailability of skilled labor? One approach could be to better utilize existing training resources. Alternately, improved resource forecasting could result in plans that would better match the number of new employees with projected industry needs. To address these issues, a research project was undertaken by CREATE, an advanced technology research consortium at Arizona State University, to identify the resource requirements for the design and construction of a semiconductor manufacturing facility. The research study outlines the skills and labor requirements from programming (initial design) to the completion of a model base-build facility. The results from this research indicate a high demand for a skilled labor force, especially for the mechanical and electrical trades, during the construction phase. Data collected from additional fabrication facilities will help create a resource model, which will assist in forecasting the demand of skilled labor for a proposed project.

UR - http://www.scopus.com/inward/record.url?scp=2342438800&partnerID=8YFLogxK

UR - http://www.scopus.com/inward/citedby.url?scp=2342438800&partnerID=8YFLogxK

M3 - Conference contribution

AN - SCOPUS:2342438800

SN - 0784406715

SN - 9780784406717

SP - 121

EP - 129

BT - Contruction Research Congress, Winds of Change: Integration and Innovation in Construction, Proceedings of the Congress

A2 - Molenaar, K.R.

A2 - Chinowsky, P.S.

ER -