N2 - Feasibility and suitability assessments have become increasingly important for trenchless projects, as some Federal and State permitting agencies have released guidance on the information required to complete their environmental review. The Federal Energy Regulatory Commission (FERC) released guidance in October 2019, and the Pennsylvania Department of Environmental Protection (PADEP) released a draft Trenchless Technology Technical Guidance Document for use by project applicants when considering trenchless crossing methods in the Commonwealth of Pennsylvania. For complex trenchless installations and those that involve multiple permitting agencies with different guidelines, adherence to these guidelines has become increasingly important in avoiding or minimizing potential permitting and project delays. This paper reviews the requirements established by FERC and PADEP as a case study that may be indicative of the regulatory trend emerging in various jurisdictions across the nation. Public data research, geohazards evaluation, geophysical evaluation, and geotechnical investigation are describe, while following both the FERC and PADEP trenchless technology guidelines. Finally, this paper demonstrates the consolidation of data gathering and engineering analysis to select the most practical and least impacting trenchless alternative.
AB - Feasibility and suitability assessments have become increasingly important for trenchless projects, as some Federal and State permitting agencies have released guidance on the information required to complete their environmental review. The Federal Energy Regulatory Commission (FERC) released guidance in October 2019, and the Pennsylvania Department of Environmental Protection (PADEP) released a draft Trenchless Technology Technical Guidance Document for use by project applicants when considering trenchless crossing methods in the Commonwealth of Pennsylvania. For complex trenchless installations and those that involve multiple permitting agencies with different guidelines, adherence to these guidelines has become increasingly important in avoiding or minimizing potential permitting and project delays. This paper reviews the requirements established by FERC and PADEP as a case study that may be indicative of the regulatory trend emerging in various jurisdictions across the nation. Public data research, geohazards evaluation, geophysical evaluation, and geotechnical investigation are describe, while following both the FERC and PADEP trenchless technology guidelines. Finally, this paper demonstrates the consolidation of data gathering and engineering analysis to select the most practical and least impacting trenchless alternative.
UR - http://www.scopus.com/inward/record.url?scp=85125672529&partnerID=8YFLogxK
UR - http://www.scopus.com/inward/citedby.url?scp=85125672529&partnerID=8YFLogxK
U2 - 10.1061/(ASCE)PS.1949-1204.0000614
DO - 10.1061/(ASCE)PS.1949-1204.0000614
M3 - Article
AN - SCOPUS:85125672529
SN - 1949-1190
VL - 13
JO - Journal of Pipeline Systems Engineering and Practice
JF - Journal of Pipeline Systems Engineering and Practice
IS - 2
M1 - 04022008
ER -